3D Point Cloud Data Basis Shape Management for Assembly of Modularized Large and Complicated Marine Structures

Table 3

Application results of 3D point cloud data basis simulation for the leg block assembly.

DimensionsWeight (abt.)Crane capacityAdditional cost caused by construction delay in the dock
CraneMan-hourConstruction delayAdditional cost

Case  165 m × 32 m7,000 ton9,000 ton1 hour37 m/h × 1 h24,000
US dollars
Case  237 m × 34 m4,500 ton9,000 ton1 hour37 m/h × 1 h24,000
US dollars
Case  337 m × 34 m4,500 ton9,000 ton1 hour37 m/h × 1 h24,000
US dollars